Programme Evaluation and Review Technique (PERT) and Critical Path Method (CPM) (part-3)
List out all the activities involved in a project. Say, for example, in building construction, the activities are: (i) Site selection, (ii) Arrangement of Finance, (iii) Preparation of building plan, (iv) Approval of plan by municipal authorities, (v) Purchase of materials, (vi) Digging of foundation, (vii) Filling up of foundation, (viii) Building superstructure, (ix) Fixing up of doorframes and window frames, (x) Roofing, (xi) Plastering, (xii) Flooring, (xiii) Electricity and water fittings, (xiv) Finishing Þ Once the activities are listed, they are arranged in sequential manner and in logical order. For example, foundation digging should come before foundation filling and so on. Þ After arranging the activities in a logical sequence, their time is estimated and written against each activity. For example: Foundation digging: 10 days, or 1½ weeks. Þ Some of the act...